QAT Phase13 GTC/736C&E/2015
  • Project NameQATAR Phase 13 GTC/736C&E/2015 Project
    QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13
  • Scope of Supply
    • 48.4 km of 400 kV 2,500 mm² Cu/XLPE cables and 78 sets of cable accessories
    • 144 km of 220 kV 2,500 mm² Cu/XLPE cables and 240 sets of cable accessories
    • 337.8 km of 132 kV 2,000 mm² Cu/XLPE cables and 546 sets of cable accessories
  • Contract ValueApproximately KRW 262.3 billion (USD 212.4 million)
  • Contract PeriodApr. 2017 to Jun. 2023
  • Scope of Work400/220/132 kV EPC turnkey project covering 24 circuits, 15 routes, and 183 km
  • Project SignificanceQatar's largest-ever underground cable project, with orders secured for more than 70% of total demand
    The largest underground cable project awarded to a Korean cable manufacturer in the Middle East