114 km of 400 kV XLPE cables, 2,500 mm² / Joints (210 sets) and terminations (12 sets) / Turnkey construction including PD, DTS, and testing for 2 circuits, cable laying, and civil works
Contract PeriodOct. 2019 to Oct. 2020 (5 years of warranty and maintenance, through Oct. 2025)
Scope of WorkFull turnkey construction of two 400 kV circuits over a route of approximately 19 km
Project SignificanceOur first large-scale 400 kV turnkey contract in Bahrain broke into a market dominated by European competitors and demonstrated LS's technical capabilities beyond 66 kV and 220 kV. It established a foundation for participating in the 400 kV market, where further orders are expected.