Scope of Supply66 kV IPC supply and installation in SG / 66 kV PCC and ICC cable supply and installation in TW
Contract ValueEUR 5,914,857 (installation), approximately KRW 7.69 billion
Contract PeriodAug. 2020 to Sep. 2022 (estimated)
Scope of WorkCable laying, jointing, and commissioning tests at the offshore substation (OSS) / Jointing and commissioning tests at wind turbines
Project SignificanceOur experience in executing the first array project in Taiwan will provide a foundation for further expansion in the offshore wind power market.